The trusses were delivered late last week. We had to do some engineering checks regarding load bearing areas to make sure the roof would stay up. Lori caught them using the crane to load the trusses up top. They used the crane to get all the pieces up in order, and the workers moved the smaller ones in place. The crane was used to get the more massive pieces lined up. It took about 3 days, and they have begun to put on the roof panels.