New stuff to report at last. The shipment of windows arrived and they began to put them in. Almost complete. The sliding doors are very nice and sturdy. These really change the feel from inside.
Caissons were also drilled to support the deck in back and front, and they put up the roof/overhang for the front porch. The large decorative trusses are starting to go up in front as well. A mistake was made in the angled truss over the garage, where a bigger beam was supposed to be used o they're going to have to yank them.
Next work up is to finish the windows, start work on the deck, and get the basement ready with the radiant system and pour the slab.