They were supposed to put insulation over the pipes where the refrigerator and island will be. I didn't make it out to check on them (now it's covered and we'll never know). Lori was quick enough to realize that it probably wouldn't be a good idea to pump heat under the refrigerator. The heating guys didn't come up with it, and we were disappointed by that. Who knows what else might be missed.



No sleepers in the nook/mudroom. This will be a tile floor.

The wood floor gets delivered in about 2 weeks, and has to sit a week to acclimatize. Next steps will be some tiling, doors, start some trim, start the stone wall around the fireplaces.