Saturday, January 28, 2006
Concrete forms for Foundation walls
Work started on putting the forms up 3 days ago. It took several days to get the forms in to begin the work.
The near wall and wall to the right (front of the house), are about 12 feet high. About 2 feet of fill and concrete slab will go in the bottom, making a total of 10 foot walls for the basement.
They're still working on putting up the far side walls (south), which will step down in height and be above ground.
Cement pouring should begin Tuesday or Wednesday.
Pics on flickr